Hi,

We are using Oracle R12.1.3.4, we want to enable E-Signature for work order creation. but when completing the work order, we are not getting the e-signature screen. the work order is getting completed.

we referred Steps To Setup EAM With ERES During Work Order Completion? ( Doc ID 1454731.1 )

and found that the Business event for work order is not subscribed. it is enabled but no subscription.

1. how to complete the subscription?

2. we also checked the file version of eamwocomps.wfx

[oratest@us6-erpapp-p03 12.0.0]$ strings -a ./patch/115/xml/US/eamwocomps.wfx|grep Header

<!-- $Header: eamwocomps.wfx 120.1 2005/07/07 04:53:05 mkishore noship $ -->

As per this Metalink Note: even after applying patch, the issue is not resolved. Please let us knowhow to get EERES enabled in work order completion in EAM.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center