Hi,

We require ECOs to be used for all changes to Items and Routings and have therefore set BOM: Standard Item Access to NO for all users.

A Serialization Start Op Seq can usually be defined on the Routing Details screen, but this field is not available on the Routings tab in the ECO although the neighbouring fields do appear.

How can the value of the Serialization Start Op Seq be set when uisng ECOs?

Thanks!