Don't want MRP to create planned orders for Sub assemblies

edited Mar 25, 2015 1:03AM in Value Chain Planning - EBS (MOSC) 11 commentsAnswered

This is MRP planning.

Have Structure as below:

FG1(Make)

-SA1 (Make item but planned from 3rd party)

-RM1(Buy)

-RM2(Buy)

SA1 (Make Item)

-RM3(Buy)

-RM4(Buy)

In MRP planning,i don't want MRP to create planned orders for SA1(as the planning is done from other tool) but at the same time lead time for this SA1 should be considered for FG1.

Please suggest.

Thanks,

Jey