Split A1 cost component

edited Oct 24, 2017 2:21PM in Manufacturing - JDE1 (MOSC) 3 commentsAnswered

Hi,

I've received a requirement from finance team to exclude the container from Materials (A1) cost component and use a different cost component for it.

Currently container is part of the BOM, issued to the WO and summarised on A1 as materials, is there a way to split A1 cost component into A1 and XA for example?

According to E1 manual, this is not possible, but maybe someone had a similar issue and can help me.

The workaround I'm thinking of is to have

- 0 cost on containers to avoid summarising its cost into A1

- Use X9 cost component for container's cost