Hello all,
We are working with a Acme Packet 1100 before installing on Customer facility. After reading the specific documents for this model, I have one doubt. In Acme Packet 1100 Hardware Installation Guide it is stated how to deply it on many scenarios, like rack mounted. For example, it is clearlly explained how to place it on a 4-post tapped-hole equipment rack and a full description on how to power on. Meanwhile, there is a missing explanatin about how to place the external power supply in such kind of racks. This comment also apply for a 2-post tapped-hole equipment rack.
Where should the Power Supply be placed? I coudnt figure out how to join the power supply to the chassis and just put it on the top of chassis dont seem the most ellegant solution...