rccp in ascp/opm
I am wondering how to do true RCCP in OPM. OPM does not support Bill of resource. RCCP is typically done at Aggregate resource level and in weekly/monthly bucket. I know, I can do capacity Planning at individual resource level, but that is not exactly RCCP.