MRP planning fence rule and planning fence days
I run the MRP with monthly periods PO "Planning Horizon Periods"
So, my period is from 04/01/2015 until 04/30/2015
The item setup in branch plant = planning fence rule C and planning fence 10.
That means in April the first 10 days work with only customer demand and after it greatest of forcast (FC) or customer demand.
End of month I have FC and in the time of the planning fence 10 I have a sales order.
April is one period, so I like to have the greatest value FC or customer demand.
But I have a sales order in the first part of the planning fence rule and change within the month to the second part greatest of.