Work Order Duration error?

edited Apr 9, 2015 1:26AM in Enterprise Asset Management - EBS (MOSC) 12 commentsAnswered

Hello Experts,

I am facing an unusual behaviour in the EAM Work order duration.

I created a Work order with 2 operations op1 & op2, op1 has 2 resource worked for 0.5hours & op2 has 3 resource worked for 2.5 hours. Total maintenance work is for 3 hours and Total manhour is 8.5.

Detail explanation:

2Plumber * 0.5hours     =1 Manhour

3Helper * 2.5hours     =7.5 Manhour

Total Duration=3hours, Total Manhour is 8.5.

How to enter op1 & op2 with the above manipulations to see the duration as 3hours, as i tried with all the combination but not getting proper durations.

Kindly help on the above and respond asap.

Thanks,

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center