ATP not considering MFG lead time for Make Item
Dear Friends,
We are on Oracle 11i and have issue in which ATP does not populate the Schedule Ship date (SSD) correctly for make items. Basically if the child component (C) are available same day, it populates the SSD for parent item as sysdate not considering the manufacturing lead time. System is behaving as per 'ATP based on Collected Data'.
We have checked the lead time setup for parent item (P). It is populated with Processing Lead time=14, Cumulative Total=14 and Lead time Lot Size=1. So it seems fine. Moreover, it seems to be working fine in Dev instance. Following are the pegging details in Production and development for your reference.