Hi,

Just wanted to confirm my understanding. We are going OPM Live on 1st May and suppose we load Opening cost  for May period after 1 week of OPM Live and also do SLA setup after 1 week of OPM Live, there will be no impact, right? As we will run ACP  after 1 week only. Also accounting will be generated properly?