Planned Value and Earned value are different while same sch% complete and performance % complete

edited May 6, 2015 10:44PM in Primavera (MOSC) 4 commentsAnswered ✓

Planned Value and Earned value are different in some activity in my project while:

1- sch% complete and performance % complete are same

2- no resource curve assigned

3- no future bucket planning used

4- no project baseline

considering P6 PV and EV formulas:

PV= schedule% complete * BAC

EV=Performance % Complete * BAC

we should have same EV and PV but it is not happened for some of my activities.

below screenshot is self explanatory.


Any Idea how to fix this issue please?


Regards,

Manochehr