EDD Constrained plan not respecting Fixed lead time
EDD Constrained plan is not respecting fixed lead time for Make item
Say we have Make ItemA with 10days Fixed LT and demand date on 30May.
Item B is a component for this make itemA and we expect Item B planned order demand on 20th May respecting the LT.
But we are seeing Item B planned order demand date same as 30May. Any suggestions pls...