EDD Constrained plan not respecting Fixed lead time

edited May 18, 2015 10:01AM in Value Chain Planning - EBS (MOSC) 2 commentsAnswered

EDD Constrained plan is not respecting fixed lead time for Make item

Say we have Make ItemA with 10days Fixed LT and demand date on 30May.

Item B is a component for this make itemA  and we expect Item B planned order demand on 20th May respecting the LT.

But we are seeing Item B planned order demand date same as 30May. Any suggestions pls...