WIP Assembly Completion Transaction showing 0 (zero) cost

edited May 20, 2015 7:35AM in Discrete Manufacturing - EBS (MOSC) 3 commentsAnswered

Hi,

We have couple of standard WIP discrete jobs in our system that have completed successfully. However the WIP Assembly Completion Transaction cost is showing 0 (zero) in WIP value summary for some transaction which is affecting the average item cost.Our organization is Avg Costing org. Some of the jobs are already closed. Kindly suggest how it happened and how can we correct the same.

I am attaching screenshot of WIP value summary showing 0 value assembly completion transaction.

Regards,

Bhargav