Suggested start date is not considering processing Lead time of Source Org
Hi All,
We are using IR/ISO in our organization, where Org A is sourcing from Org B
Item: XYZ Org: A Org: B
Preprocessing LT 2 days 2 days
Processing LT 8 days 8 days
Post Processing LT 1 day 1 day
Intransit LT 5 days
Fixed LT 8 0
Variable LT 0 0
Sugg Due Date - Demand Date
Sugg Dock Date - Due date - Post Processing LT
Sugg Ship Date - Dock Date - Intransit Lt
Sugg Start Date - Ship Date - Processing LT (of Org – This should be 8 days where as I find 0 days from the plan output.
Sugg Order Date - Start Date - Pre Processing LT