Suggested start date is not considering processing Lead time of Source Org

edited May 23, 2015 10:01AM in Value Chain Planning - EBS (MOSC) 3 commentsAnswered

Hi All,

We are using IR/ISO in our organization, where Org A is sourcing from Org B

Item: XYZ  Org: A                      Org: B

Preprocessing LT 2 days             2 days

Processing LT 8 days                8 days

Post Processing LT 1 day           1 day

Intransit LT 5 days

Fixed LT 8 0

Variable LT 0 0

Sugg Due Date - Demand Date

Sugg Dock Date - Due date - Post Processing LT

Sugg Ship Date - Dock Date - Intransit Lt

Sugg Start Date - Ship Date - Processing LT (of Org – This should be 8 days where as I find 0 days from the plan output.

Sugg Order Date - Start Date - Pre Processing LT

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center