R12 Budget contral and encumbrance
Hello
we are in r 12.1.3.
We want to implement Budget control to manage /control the amount it is expenses in purchase orders.
Is it mandatory to use Budget Control and Encumbrance in PO? I mean I will have a budget in GL and every time we approve a PO I want the application tell me if I have enough money in my budget to buy it or not. I thought it was enough with Budget control, but it seems that I must enable the encumbrance in PO.
Is that right?
Thanks.