Is it possible for PM work orders to be generated based solely on actual meter readings? i.e. vehicle maintenance every 5000 miles not using rate per day, which varies.

If so, I need to know how to set up the following to accomplish it.

Meter: rate per day, number of past readings, and should initial reading have a value?

PM Schedule: Scheduling Options- use Base Meter or Date?,

I have researched on MOS and MOSC and found conflicting solutions.