Intransit days in processing Rules offsetting Sales Order Request Dates
Hi,
We are working on a Firm Orders Scenario in Oracle Release Management where we have the below setups in Processing Rules.
Intransit Days - 2 days
Exclude Non-Workdays - Checked
Calculation Basis - Shipped Lines
Customer Request Date Type - Arrival.
RLM Date Type - Deliver
Firm time fence set to 15 days
The expectation is within the Firm time fence window, if there are any demand - the system is supposed to create a Order with a Request date same as the date in RLM and offset the schedule ship date by the Intransit days. When we test it out for the same scenario, we are seeing that the Request Date and SSD are the same and both of them are getting offset by the Intransit days.