New Task set up error
Hi
A new task is trying to be created on a project but the following error keeps appears
You have charged an expenditure item against this task with an expenditure item date that is after the task end date. Please revise the task end date so that it is the same as or later than the following expenditure item date: '25/05/2014'.
The dates being input are start date 28/05/2015 and End date 31/03/2019.
Any ideas?
Thanks
Jeanette