Multiple Resources on an Activity
Lets take an Activity with Multiple resources
Resource Budget Units Actual Units Remaining Units At Comp Units
Carp 500 0 500 500
Labr 250 0 250 250
Iwrk 75 0 75 75
when you apply the units pct comp. it takes the total hours and use it to calculate the individual resources. How can I change the units pct comp for each resource independently through a global change or something