Internal Requisitions not getting approved
I have done a complete setup for 2 INV orgs under one OU. I can create POs/Reqs for these 2 Orgs & receive it too.
I have also done the necessary setups for ISO. (Metalink Note 1384716.1)
After creating a IR when i press Approve, the IR is not getting approved. It remains in Incomplete Status.
I have not changed the Approval groups/limits or assignments.
What can be the issue here ?
Inter-Org transfer is not the option as it will mes with planning/demand/supply at both places.
Thanks in advance.