The batch complete less than sum of batch issue and step issue in same period
1. lot cost details is not right ;
2. the sub accouting of journal is not right
why I think so: I will explain to you
(I run all cost process : gmf period close\GMF Recreate Batch / Period Layers\ actual cost \actual cost update\lot cost process\OPP\Create acounting)
sample batch in Org_code:Z06 \ batch no:134
1. first: I run opm cost programs (include actual cost process\lot cost process\OPP\Creacte accounting and...)
2. then:I check it's journal entry lines about the batch inclued three account event type:
Batch Completion 、Step Completion、Batch Release
3. I Find the Journal lines below