Primavera P6.8.3 question about Stacked Histograms
This is the first time I've used a 'community' service, so please forgive me if I don't get it right first time.
Primavera P6.8.3 question about Stacked Histograms
I'm running 30+ projects and using standard resource profiles for each Engineering discipline - please see attached Standard Resource Profile
Each of our projects has a Project Code of Priority 1, 2 or 3, and rather than use the standard Stacked Histogram of the disciplines stacked on top of each other per time period, I'd like to see them stacked by priority for a single discipline - as in attachment Resource Stacked Histogram by Priority. This is a dump from P6 into Excel. With the information already being in P6, is there some way I can get it out directly without going through the excel route?