Hi,
I have a WIP Job with 2 operations.
10- Inhouse operation
20 - OSP
System Created a Requisition and I have created PO and then received it.
Completed the WIP job and I could see Po still shows in Commitment not on the expenditure.
Rest of all the WIP are showing as Expenditures.
Thanks,