Has anyone had an issue with dependent demand multiplying with every MRP run (unless you clear tables)?
I have one item set up as phantom. The demand flows as it should, creating a work order for the phantom, and a planned order for the dependent item. However, if I run MRP again, the planned order for the dependent doubles, and triples with a third run, etc. NO other items duplicate in this way - only the dependent. Any idea what could be causing this?? **Note: this only happens when using Simple Consolidation method. I tested using branch relationships and did not have this issue**