Dear All,
Due to a bug on Discrete Job WIP completion page, users have created assemblies with revision (F) which is not yet ECO implemented. The user has not implemented the ECO and does not want to either, instead he wants to use the current revision (0) in another job as a component. So we need to change the stock qty from revision (F) to revision (0). Now since (F) revision is not implemented we cannot perform miscellaneous issue nor can we return the WIP Discrete Job since the Job and inventory period are both closed. We are exploring the option of