Resource availability

edited Jul 15, 2015 10:03AM in Value Chain Planning - EBS (MOSC) 2 commentsAnswered

 

In my Production Scheduling log, I see the following error for many items. "Work Order # was not correctly specified. Item # is not produced by this Work Order."  THis is preventing many work orders from importing into the model.

I checked knowledge base and it pointed to resources not being available for the work order.  When i check, everything in the work order looks good.  Resources are open and not applied.  Resource and calendar/shift setups are also fine.

What am i missing?