How do I get a resource planning list to show in MicroSoft Projects?
I am trying to use MS Projects integration with Oracle Projects. In QA environment, I had the resource planning list with employees showing up in MS Project so I could assign resources in MS Projects at task level and send back to Oracle Projects. AFter a refresh, this is not working. I ran the UPG Resource List to Resource Planning List job and it still does not show up in MS Projects. I have checked and looked and can't find the problem. Anyone know the different things i should look at and check to resolve this? The resource list is