Capacity planning: CRP
Hi,
In The WC load P3313, the time buckets comes from the MRP R3483. It is set to 5 days-7 weeks- 10 month
The problem issue is within the 5 days. I have a WO that covers the need for a week in terms of capacity. the WO starts on monday and ends on friday.
The requested day is on friday. The routing is one operation seq. And the system uses requested dates for the capacity calculation
the load says that on friday I am overloaded. When I start declaring production on monday and tuesday then the load start decreasing and the % capacity used becomes more reasonable.