Resources cost deleting Automatically

edited Jul 31, 2015 1:55AM in Primavera (MOSC) 2 commentsAnswered ✓

Hi

I am facing a bigger problem which self never faced before.


Cost added in Activities through Resources manually, where as Resources > "calculate cost from units" has unchecked.  

After assigning Baseline in proper manner when I am trying to updating any thing in Activity or resources all cost deleting it self.

why it is happening to me ? Total 780 activities assigned with resources & cost. Every time I am restoring my project from backup to test but unable to crack.

Pl help me out

Regards

Madan