Hi
I am facing a bigger problem which self never faced before.
Cost added in Activities through Resources manually, where as Resources > "calculate cost from units" has unchecked.
After assigning Baseline in proper manner when I am trying to updating any thing in Activity or resources all cost deleting it self.
why it is happening to me ? Total 780 activities assigned with resources & cost. Every time I am restoring my project from backup to test but unable to crack.
Pl help me out
Regards
Madan