Manufacturing Planning
What is proper sequence to run the enterprise one planning program.
Which Option is correct below 5 options
A) 1. Forecasting, 2.Rough Cut Capacity Requirements Planning, 3. Material
Requirements Planning, 4. Master Production Scheduling
1. Material Requirements Planning, 2. Forecasting, 3. Master Production
Scheduling, 4. Rough Cut Capacity Requirements Planning
C) 1.Forecasting, 2. Master Production Scheduling, 3. Rough Cut Capacity
Requirements Planning, 4. Material Requirements Planning (*)
D) 1. Forecasting, 2. Material Requirements Planning, 3. Rough Cut Capacity
Requirements Planning, 4.Master Production Scheduling
E) 1. Rough Cut Capacity Requirements Planning, 2. Forecasting, 3. Master
Production Scheduling, 4. Material Requirements Planning ?????????????