Hi All,

Our current practice with respect to configuring 'Resource Access' to Users (Resource Managers) is providing them 'All Resource' access. We were interested in restricting such Users to be able to manage only specific Resource hierarchy in P6. By configuring this access to a particular resource R1, the User User1 is able to see resources only from R1 hierarchy on both

- Resources > Administration page - for modification

- Projects > Activities > Assignments (Detail Window) - for Project Activity Assignments

which is as expected.

Additionally, User1 can see Resources from other hierarchies in Activities - Assignments window, in cases where they are already assigned to the Project to which she has access.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center