Project Burdening: Inventory and WIP source
Dear All,
Modules: Project Costing, Project Manufacturing, Inventory, WIP, financials
Design:
1) Collect the cost from Inventory and WIP.
2) Generate Accounting in Manufacturing.
3) Transfer the Cost from manufacturing to Projects through Project Manufacturing.
4) Send the data to GL from Manufacturing
This scenario projects is used for information/reporting purpose.
Now the new requirement is to capture manufacturing overheads in projects by using project burdening feature. i know burdening can be implemented for transaction entered in projects/or transaction source that allows burdening in projects.
Inventory and WIP transaction source doesn't allow burdening in projects as the 'Import burden amounts' flag is checked and seeded(cant be changed)