How to make Remaining unit & Budgeted unit same
Hi
Lets one Activity duration 10 days
one Resources added, In time of adding following result comes
Remaining Units/Time Budgeted Unit Remaining Unit
8hr/d 80 80
When I am changing Remaining Units/Time to 2hrs/d it is not changing Budgeted Unit where as Remaining Unit changes to "20"
My Question - does it effect in schedule if I will not change the Budgeted Unit manually ??
Q2 - How to do Global change for Remaining Unit = Budgeted Unit for all activities.
Note - Base line has not created. Resources - Auto Compute Actuals & Cost calculate from units both are unchecked.
Regards
Madan