How to make Remaining unit & Budgeted unit same

edited Aug 13, 2015 12:27AM in Primavera (MOSC) 1 commentAnswered ✓

Hi

Lets one Activity duration 10 days

one Resources added, In time of adding following result comes

Remaining Units/Time           Budgeted Unit               Remaining Unit

8hr/d                                             80                              80

When I am changing Remaining Units/Time to 2hrs/d it is not changing Budgeted Unit where as Remaining Unit changes to "20"

My Question - does it effect in schedule if I will not change the Budgeted Unit manually ??

Q2 - How to do Global change for Remaining Unit = Budgeted Unit for all activities.

Note - Base line has not created. Resources - Auto Compute Actuals & Cost calculate from units both are unchecked.

Regards

Madan

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center