How to Report Time in MES for the Resource that is not part of the Job Routing.
Following is the sequence of activities being performed:
1. Created a Discrete Job and Released
2. Assembly has two Resource ( R1 & R2) in the Routing
3. Login to MES
4. Using Report Time Functionality for that Job charged R1 & R2
5. Need to charge R3( Resource) which is not part of Rounting/Job- How can this be performed?