Hi Guys,
We are on Agile 9.3.1. facing PPM module date setting issue.
Working hours set in Agile property file : 8 AM to 5 PM
Server is in CDT timezone.
OOTB : When users move the tasks to "In Process" status, the Actual Start date is being set automatically.
If users move after 4 PM, the date would be set to very next day 8 AM.
Issue is, when they move to "In Process" after Friday 4 PM, it is being set on Saturday 8 AM. We don't want to set the "Actual Start Date" to weekends.
It should be set to Monday 8 AM.
I think, to resolve the above issue, we need a PX to be scheduled at "In Process" status to change the date to Monday if it is being set on weekends.