Hi Group,

I have placed Forecast at Supply / Make Branch plant and placed some more forecast on Demand BP as well. After MRP runs, system must generate accumulated WO messages to satsify both demand which is not happening. I can see tansfer order messages for the FC placed at Demand BP, but related WO qauntity message is not been accumulated for Make BP.

FYI - I am using MRP 'Parallel' processing.  Any ideas or clues ?