Encumbarance Option in Purchasing
We are 12.1.3 and currnelty we dont have Projects module and Purchasing>Financial Option>Encumbarance> has been set up with null for 'Use requisition encumbarance',Reserve at completion, Use PO Encumabarance.
Now Project Costing module is being implemented and As per the recommendation Encumbarance Option has to be enabled for PR and PO. IF this has been enabled, then all requisitions (even without Projects) are being populated with Budget account and seeing lot of changes for Non project PR's as well.. Is there anyway like Encumbarance can be enabled only for Project based Requisitions or Purchase orders.Is there any profile or set up required to achieve this.