Over Receipt tolerance is ignored while receiving
Hello,
I have created a PO Requisition in I-Procurement for 10 quantity. While creating a receipt I entered the quantity as 50 instead of 10. The system warned but did not stop from creation of Receipt.
Referred to
The setup is already there as per the above note i.e. 'Allow Blind Receiving' is unchecked.
However, still the system does not restrict. We are using Oracle R12.1.3
Also referred to
Any views ?
Thanks