Multi Branch/Plant MRP
Hi all
I need some help, a colleague is working with a client on their multi branch/plant MRP solution in JDE. To keep it simple, they have two branch/plants, one that procures and stores raw material and the other that uses the raw material to produce finished goods, with ST/OT's used to transfer raw material between the two. Since the first branch/plant is used as the main storage, safety stock is calculated for a raw material item and sits as demand against that item at this branch/plant. An ST/OT is raised to transfer the raw material from the procurement/storage branch/plant to the