Dates problem in BI publisher reports from P6
Hi,
I created some reports from P6 reporting database using BI Publisher, the problem is that the dates that these report shows for activities starts and finish have 1 day different with what P6 shows.
for example in above screenshot the forecast dates which comes from activity finish should be 18 Jun 2014 but it shows 17 Jun. it happens for all activities.
Appreciate if anyone can help me on this error.
Regards,
Manochehr