PO sequence not following Requisition Sequence
Hi All - Below is the test case.
---------------------------------------------------
Create Multi Year Requisition
Line 1) for year 2015
Line 2) for year 2016
Line 3) for year 2017
Convert to RFQ. Now Covert to PO.
PO line sequence is
Line 1 corresponds to line 3 of requisition
Line 2 corresponds to line 2 of requisition
Line 3 corresponds to Lne 1 of requisition
We need to same sequencing as is there in requisition to avoid confusion. Is this a bug or we are missing something ?