P6 Project Earned Value Report in BI Publisher

edited Sep 29, 2015 10:01AM in Primavera (MOSC) 1 commentAnswered

There seems to be an issue on how the CPI and SPI is being calculated in the default report "Project Earned Value" in BI Publisher.  This report is located under the P6Reports Project folder.

What I expecting is the CPI and SPI have plotted points along the timeline which would be calculated by each periods Earned Value / Planned Value and the Earned Value / Actual Cost.

Can these reports use Actuals from the Financial Periods in the p6activityperiodactual instead of the p6projectspread?