P51412 not calculating the correct Remaining to complete
P51412 not calculating the correct Remaining to complete for ex:
revised budget=677570, actual current=26046, actual to date=59891 remaining to complete=Negative 59891, %comp=8.8 over/under= Negative 677570 MC=T ?
Thanks
0