Update "Actual Cost" from CM?
When CM & P6 projects are linked, For each contract you can create or update the document as an activity. I am able to create/update the p6 activity with Responsibility Code, Contracts and Expense Item that includes: Cost Account & Budget. When I create and approve an Payment Req, the Actual cost isn't updated following another import to update the information. What could be the cause of the non-update? Any help is greatly appreciated.