WO Start Date calculation for Process Manufacturing through Planning
Hi,
I need a help in WO start Date Calculation
My Scenario is
Process Manufacturing
Co Product Lead time per unit is 18
Process Lead time per unit is 18
I have a forecast for the Co-product 100 (i.e. Process Qty 6)with Requested date 31/10/2015
While Processing R3482, I am having the Order message for Process start date calculated as 23/10/2015 and Rhisequested date as 30/102015.
I need your help in understanding this
Regards