P3404 Process Mfg and By-product settings for demand planning
Hi all,
I'm trouble shooting some MRP issues and I'm not sure if our co/by table is set up correctly. We're process manufacturing and generate multiple by-products that are included in the P3404 table. I am seeing conflicting information where sometimes these are set at 100% planning and 100% cost and sometimes 0% planning and 0% cost. The co-products appear to be correct at 100% cost and 0% plan with the process part getting 100% of the planning. So, should by-products get set to plan at 100% or should they also be included as part of the process part's planning process?