How to avoid Resource Usage getting rounded to Minutes in ECC plan

edited Oct 13, 2015 5:02PM in Value Chain Planning - EBS (MOSC) Question

Hi Experts , Please provide suggestion  for below scenario of ours

Resource Usage = 0.009259 Hrs

Scheduled Quantity = 1 EA

Expected Resource requirement = 0.009259 Hrs

System shows resource requirement = 0.016667 Hrs

I think system is doing below calculation

Resource Usage = 0.009259 hrs = 0.55554 Mins . This is rounded to 1 min

Resource Requirement =1/60 hr = 0.0166667

Resource requirement is inflated by 1. 8 times ( 0.0166667/0.009259) = 1.8


How to avoid this rounding . This is causing huge discrepancy in resource loading

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center