Calendar in P6 is Limited to 2049
Hi,
One of our Primavera Users built a Long Range Plan going all the way to 2053.
The problem:
He can see the 2050 Calendar in P6 but as soon as he select a date in 2050, it considers this date to be 1950 date and does not allow to pick.
Have you noticed this type of problem in any of your schedule that goes beyond 2050. Anything up to 2049 works.
Is there any work around or a fix you can recommend?
Thank you
Rufran (102215)