When we rebook a contract with an arrears payment schedule I am seeing that the adjusted amount is billed on the rebook date instead of the scheduled date. For Example if we have the below schedule

6

10,150.00

2-Jul-15

1

474,150.00

2-Jan-16

If I rebook the contract on 27th Oct and adjust 2nd Oct payment to 20150 as below

Periods

Amount

start date

3

10,150.00

2-Jul-15

1

20,150.00

2-Oct-12

2

10,150.00

2-Nov-15

1

474,150.00

2-Jan-16

  System is create a new AR invoice due on 27th Oct instead of 2nd Nov. is this expected system behavior. We want the updates to schedule to bill on scheduled date.


Regards

Geeta

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center