Supplier Production Plan as Supply Schedule to ASCP
Hi All,
We are working with a supplier who provide us very critical components.
We cannot promise our end items without these components.
We are working with the supplier as key customer for them and provide our forecast. In turn supplier provides us information about allocated capacity and production plant for out items.
We need to use their production plan as supply schedule in ASCP and constraint our ASCP Plan based on these critical items.
Can someone guide me on how can we achieve this?
We get data in excel files. Based on our ASCP plan run it becomes a discussion point of the S&OP. That will help us tweak the combination of items for supplier production plan.